Description:
1
P2 Application:
1
Environmental Benefits:
This project has reduced one uracil herbicide in the waste stream by 8,900 lb/yr. It is expected to reduce the quantity of another uracil herbicide in the waste stream by 119,000 lb/yr. Total organic carbon (TOC) loadings to the site's wastewater treatment plant from uracil herbicide production will be reduced by 41% overall. Additionally, hydraulic loadings will be reduced 51%, and EPCRA emissions/wastes and uracil herbicides waste will also be reduced.